On 12 July 2010, ThyssenKrupp CSA successfully commissioned its new blast furnace No. 1. This article describes the main characteristics of the blast furnace, the main stages during commissioning, from basic design until blow-in. The charging schedule, blasting schedule and the first operational results after start-up are discussed. Source