Digby Wells Environmental

Pretoria, South Africa

Digby Wells Environmental

Pretoria, South Africa
SEARCH FILTERS
Time filter
Source Type

The start of early-works construction for the main production shaft at the Platreef platinum-group metals mine in South Africa highlights Ivanhoe's achievements in a busy first quarter TORONTO, ONTARIO--(Marketwired - May 11, 2017) - Ivanhoe Mines (TSX:IVN)(OTCQX:IVPAF) today announced its financial results for the first quarter ended March 31, 2017. All figures are in U.S. dollars unless otherwise stated. Ivanhoe Mines is a Canadian mining company focused on advancing its three mine-development projects in Sub-Saharan Africa: the Platreef platinum-palladium-gold-nickel-copper discovery in South Africa; and the Kamoa-Kakula copper discovery and the Kipushi zinc-copper-lead-germanium mine in the Democratic Republic of Congo (DRC). The Platreef Project is owned by Ivanplats (Pty) Ltd., which is 64%-owned by Ivanhoe Mines. A 26% interest is held by Ivanplats' historically-disadvantaged broad-based, black economic empowerment (B-BBEE) partners, which include 20 local host communities with a total of approximately 150,000 people, project employees and local entrepreneurs. In January 2017, Ivanplats reconfirmed its Level 3 status in its third verification assessment on a B-BBEE scorecard. A Japanese consortium of ITOCHU Corporation and its affiliate, ITC Platinum, plus Japan Oil, Gas and Metals National Corporation and JGC Corporation, owns a 10% interest in Ivanplats, which it acquired in two tranches for a total investment of $290 million. The Platreef Project hosts an underground deposit of thick, platinum-group metals, nickel, copper and gold mineralization in the Northern Limb of the Bushveld Igneous Complex, approximately 280 kilometres northeast of Johannesburg and eight kilometres from the town of Mokopane in Limpopo Province. On the Northern Limb, platinum-group metals mineralization is hosted primarily within the Platreef, a mineralized sequence that is traced more than 30 kilometres along strike. Ivanhoe's Platreef Project, within the Platreef's southern sector, is comprised of three contiguous properties: Turfspruit, Macalacaskop and Rietfontein. Turfspruit, the northernmost property, is contiguous with, and along strike from, Anglo Platinum's Mogalakwena group of mining operations and properties. Since 2007, Ivanhoe has focused its exploration and development activities on defining and advancing the down-dip extension of its original discovery at Platreef, now known as the Flatreef Deposit, which is amenable to highly mechanized, underground mining methods. The Flatreef area lies entirely on the Turfspruit and Macalacaskop properties, which form part of the company's mining right. The Platreef Project reached a total of 7,121,029 million hours and 16,055 lost-time injury-free hours worked in terms of the Mines Health and Safety Act and the Occupational Health and Safety Act of South Africa by the end of March 2017. Two medical treatment cases and two lost-time-accidents occurred during the first quarter of 2017. The Platreef Project continues to strive toward its workplace objective of an environment that causes zero harm to any employees, contractors, sub-contractors and consultants. Shaft 1, with an internal diameter of 7.25 metres, will provide access to the Flatreef Deposit and enable the initial underground capital development to take place during the development of Shaft 2 and ultimately will become the primary ventilation intake shaft during the project's four Mtpa production case. Following the successful commissioning of the stage and kibble winders and ancillary equipment, the permanent sinking phase started in July 2016. The initial sinking phase was completed to 107 metres below surface and the main sinking phase has been initiated. Shaft 1 had reached a depth of 346 metres below surface as of May 8, 2017. An average sinking rate of 45 metres per month is expected during the main sinking phase. The shaft includes a 300-millimetre concrete lined shaft wall. The main sinking phase is expected to reach its projected, final depth of 980 metres below surface in 2018. Shaft stations to provide access to horizontal mine workings for personnel, materials, pump stations and services will be developed at depths of 450, 750, 850 and 950 metres below surface. Figure 2: Members of the Platreef sinking team underground in Shaft 1, which was at a depth of 346 metres below surface on May 8, 2017: http://media3.marketwire.com/docs/1094410-F2.pdf Shaft 2 will be located approximately 100 metres northeast of Shaft 1. Shaft 2, with an internal diameter of 10 metres, will be lined with concrete and sunk to a planned, final depth of more than 1,100 metres below surface. It will be equipped with two 40-tonne rock-hoisting skips with a capacity to hoist a total of six million tonnes of ore a year - which will be the single largest hoisting capacity at any mine in Africa. The headgear for the permanent hoisting facility was designed by South Africa-based Murray & Roberts Cementation. The early works for Shaft 2 will include the excavation of a surface box cut to a depth of approximately 29 metres below surface and the construction of the concrete hitch (foundation) for the 103-metre-tall concrete headgear (headframe) that will house the shaft's permanent hoisting facilities and support the shaft collar. The early works are planned to commence in Q2 2017 and will take approximately 12 months to complete. Figure 3: Illustration shows two perspectives of Shaft 2's 103-metre-tall concrete headgear, the hitch (foundation) and internal permanent hoisting facilities: http://media3.marketwire.com/docs/1094410-F3.pdf Ivanhoe plans to develop the Platreef Mine in phases. The initial annual rate of four million tonnes per annum (Mtpa) is designed to establish an operating platform to support future expansions. This is expected to be followed by a potential doubling of production to eight Mtpa; and then a third expansion phase to a steady-state 12 Mtpa, which would establish Platreef among the largest platinum-group-metals mines in the world. Ivanhoe has made good progress on advancing the feasibility study of the first phase of development of the Platreef Mine. The study, which began in August 2015, is being prepared by principal consultant DRA Global, with specialized sub-consultants including Stantec Consulting, Murray & Roberts Cementation, SRK Consulting, Golder Associates and Digby Wells Environmental. The study is planned for completion in Q2 2017. Metallurgical testwork has focused on maximizing the recovery of platinum-group metals and base metals, also while producing an acceptably high-grade concentrate grade for sale to third parties. The three main geo-metallurgical units and composites have produced concentrate grades of approximately 85 to 110 grams per tonne platinum, palladium, rhodium and gold (3PE+gold) at good platinum-group-elements (PGE) recoveries (86% to 88% 3PE+gold). Comminution and flotation testwork has demonstrated that the optimum grind size of 80% passing 75 micrometres, in one stage of milling is sufficient to achieve the PGE recoveries referred to above. This simplifies the circuit and should enable Ivanhoe to optimize the capital and operating cost of the concentrator. The flow sheet for phase one comprises a four Mtpa, three-stage crushing circuit, which will feed into two parallel milling-flotation modules, each with a capacity of two million tonnes per year. Flotation is followed by a four Mtpa tailings-handling and concentrate-thickening, filtration and storage circuit. The selected mining areas in the current mine plan occur at depths ranging from approximately 700 metres to 1,200 metres below surface. The main access to the Flatreef Deposit and ventilation system is expected to be through four vertical shafts: 1, 2, 3 and 4. Shaft 2 will host the main personnel transport cage, and the material and ore-handling system; shafts 1, 3 and 4 will provide ventilation to the underground workings. Shaft 1, now under development, also will be used for initial access to the deposit and early underground development. The planned mining will incorporate low-cost, mechanized mining methods, including long-hole stoping and drift-and-fill mining. Mined-out areas will be backfilled with a mixture of tailings from the processing plant and cement. The ore will be hauled from the stopes to a series of ore passes that will connect to a main haulage level at Shaft 2, from where it will be hoisted to the surface for processing. The Olifants River Water Resource Development Project (ORWRDP) is designed to deliver water to the Eastern and Northern limbs of South Africa's Bushveld Complex. The project consists of the new De Hoop Dam, the raised wall of the Flag Boshielo Dam and related pipeline infrastructure that ultimately is expected to deliver water to Pruissen, southeast of the Northern Limb. The Pruissen Pipeline Project is expected to be developed to deliver water onward from Pruissen to the municipalities, communities and mining projects on the Northern Limb. Ivanhoe is a member of the ORWRDP's Joint Water Forum. The Platreef Project's water requirement for the first phase of development is projected to peak at approximately 10 million litres per day, which is expected to be supplied by the water network. Ivanhoe also is investigating various alternative sources of bulk water, including an allocation of bulk grey-water from a local source. The Platreef Project's electricity requirement for a four Mtpa underground mine, concentrator and associated infrastructure has been estimated at approximately 100 million volt-amperes. An agreement has been reached with Eskom, the South African public electricity utility, for the supply of phase-one power. Ivanhoe chose a self-build option for permanent power that will enable the company to manage the construction of the distribution lines from Eskom's Burutho sub-station to the Platreef Mine. The self-build and electrical supply agreements are being formulated. First phase of the relocation of informal graves completed; second phase underway On February 2, 2017, a South African judge issued a ruling in favour of Ivanplats clearing the way for the company to proceed with the relocation of informal graves in the vicinity of its Platreef Mine development project. A total of 75 informal graves were successfully relocated from land outside the perimeter of the active mine development site to new burial plots in a formal cemetery. An additional 19 locations were investigated and found not to contain human remains. The Ivanplats support program included assistance in providing new burial plots in a formal cemetery, tombstones and related services. Ivanplats plans to relocate an estimated 27 additional informal graves as part of the second phase of its relocation program after the permits for the exhumations and reburials have been received. Further phases on peripheral infrastructure areas also are planned. The relocation of remaining informal graves will not impact the development of the Platreef Project. The Kipushi copper-zinc-germanium-lead mine in the DRC is adjacent to the town of Kipushi and approximately 30 kilometres southwest of Lubumbashi. It is located on the Central African Copperbelt, approximately 250 kilometres southeast of the Kamoa-Kakula Project and less than one kilometre from the Zambian border. Ivanhoe acquired its 68% interest in the Kipushi Project in November 2011; the balance of 32% is held by the state-owned mining company, La Générale des Carrières et des Mines (Gécamines). The Kipushi Project achieved a total of 5,321,941 work hours free of lost-time injuries, equivalent to 1,694 days, to the end of Q1 2017. Malaria remains the most frequently occurring health concern at Kipushi which increased after the rainy season to an average of 26 cases per month over the quarter. In an effort to reduce the incidence of malaria in the Kipushi community, a Water Sanitation and Health (WASH) program has been initiated in cooperation with the Territorial Administrator and the local community. The main emphasis of the program's first phase is cleaning storm drains in the municipality to prevent accumulations of ponded water, where malarial mosquitos breed. The Fionet program to improve malaria diagnostics and treatment expanded to 300 Deki readers installed in 252 medical service providers in Haut-Katanga and Lualaba provinces in Southern DRC, which host Ivanhoe's Kipushi and Kamoa-Kakula projects. Deki readers provide automated readings of rapid diagnostic tests to remove the human-error factor and avoid prescription of unnecessary medication. The data is uploaded to a cloud server for analysis by the Ministry of Health in planning malaria-control measures. There were more than 40,000 patient encounters where Deki readers provided diagnostic testing during the past year, with only approximately 48% of Kipushi Project employees who were symptomatic testing positive for malaria. The Kipushi Mine, which had been placed on care and maintenance in 1993, flooded in early 2011 due to a lack of pump maintenance over an extended period. At its peak, water reached 851 metres below the surface. Ivanhoe restored access to the mine's principal haulage level at 1,150 metres below surface in December 2013; since then, crews have been upgrading underground infrastructure to permanently stabilize the water levels. Since completion of the drilling program, water levels have been lowered to the bottom of Shaft 5, which is planned to be the mine's main production shaft. The shaft is eight metres in diameter, 1,240 metres deep and approximately 1.5 kilometres from the planned main mining area. It provides the primary access to the lower levels of the mine, including the Big Zinc Deposit, through the 1,150-metre haulage level and underground ramp decline. Engineering work has focused on the upgrading of Shaft 5 conveyances and infrastructure, installation of the rock conveyor system, the stripping and evaluation of the underground jaw crusher, refurbishment of bearer sets on the main rising-water pipes, and the replacement of shaft buntons (struts that reinforce the shaft walls). A new twinned high-volume ventilation fan also has been installed and is being commissioned on surface at Shaft 4 to provide fresh air to the underground workings. Figure 5: New rollers being installed on the 1,150-metre-level ore conveyor belt as part of the infrastructure upgrading program: http://media3.marketwire.com/docs/1094410-F5.pdf In September 2016, Ivanhoe began a pre-feasibility study (PFS) on the Kipushi Project that will further refine the optimal development scenario for the existing underground mine at Kipushi. Orewin, of Australia, has been appointed the main engineering firm for the preparation of the PFS. Golder Associates, MDM, SRK, DRA, Murray & Roberts and Grindrod also have been engaged to complete various aspects of the study. The PFS will refine the positive preliminary economic assessment (PEA) for the redevelopment of the Kipushi Project that was announced on May 2, 2016. The PEA was prepared in compliance with Canadian National Instrument 43-101 - Standards of Disclosure for Mineral Projects. Highlights of the 2016 PEA, prepared by OreWin and the MSA Group (Pty) Ltd, of Johannesburg, South Africa, include: Figure 6: Upgraded supports for Shaft 5 pump columns at the 1,200-metre-level pump station: http://media3.marketwire.com/docs/1094410-F6.pdf Preparations are underway to start a 6,500-metre drilling program at Kipushi. The planned program, which is expected to begin later this month, will include six metallurgical holes and additional resource drilling in the Fault Zone and the Nord Riche and Southern Zinc zones to upgrade inferred resources to indicated resources. The Kamoa-Kakula Copper Project, a joint venture between Ivanhoe Mines and Zijin Mining, has been independently ranked as the largest copper discovery ever made on the African continent, with adjacent prospective exploration areas within the Central African Copperbelt in the DRC, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of Lubumbashi. Ivanhoe sold a 49.5% share interest in Kamoa Holding Limited to Zijin Mining in December 2015 for an aggregate consideration of $412 million. In addition, Ivanhoe sold a 1% share interest in Kamoa Holding to privately-owned Crystal River Global Limited for $8.32 million - which Crystal River will pay through a non-interest-bearing, 10-year promissory note. Since the conclusion of the Zijin transaction in December 2015, each shareholder of Kamoa Holding has been required to fund expenditures at the Kamoa-Kakula Project in an amount equivalent to its proportionate shareholding interest in the company. A 5%, non-dilutable interest in the Kamoa-Kakula Project was transferred to the DRC government on September 11, 2012, for no consideration, pursuant to the DRC Mining Code. Following the signing of an agreement with the DRC government in November 2016, in which an additional 15% interest in the Kamoa-Kakula Project was transferred to the DRC government, Ivanhoe and Zijin Mining now each hold an indirect 39.6% interest in the Kamoa-Kakula Project, Crystal River Global Limited holds an indirect 0.8% interest and the DRC government holds a direct 20% interest. Kamoa Holding Limited continues to hold an 80% interest in the project. On March 21, 2017, Ivanhoe announced that a new step-out hole, DD1124 - drilled 5.4 kilometres west of the present boundary of Kakula's current Inferred Resources - intersected a relatively shallow, 16.3-metre zone of typical Kakula-style, chalcocite-rich copper mineralization similar to holes drilled in the centre of the high-grade Kakula Deposit on the Kamoa-Kakula Copper Project. The new discovery, now referred to as Kakula West extended the length of the Kakula mineralized trend to approximately 10.1 kilometres, essentially doubling the previously estimated strike length of 5.5 kilometres contained in Ivanhoe's January 23, 2017 news release. On April 10, 2017, Ivanhoe announced the assay results for DD1124 that confirmed significant high-grade mineralization. DD1124 intersected 8.86 metres (true width) of 5.83% copper at a 3.0% copper cut-off, beginning at a downhole depth of 428.70 metres; 8.86 metres (true width) of 5.83% copper at a 2.5% copper cut-off; 16.05 metres (true width) of 4.14% copper at a 2.0% copper cut-off; and 16.05 metres (true width) of 4.14% copper at a 1.0% copper cut-off. DD1124's best six-metre intercept was 6.17 metres (true width) at 6.84% copper. In addition to DD1124, additional follow up drilling confirmed the significance of the initial discovery with two western step-out holes: Full details of the DD1138 and DD1144 intersections can be found in the April 10, 2017 news release. Excellent visual drill intercepts continue to be returned at Kakula West. The results show a rapidly growing area of shallow copper mineralization characterized by finely disseminated chalcocite in siltstone and maroon diamictite. The style and the overall geometry of mineralization are typical of the high-grade Kakula trend to the east. The Kakula Discovery remains open along a westerly-southeasterly strike. Importantly, the chalcocite-rich zone of mineralization in DD1124 was intersected at a depth of approximately 400 metres below surface, significantly shallower than several of the mineralized intercepts announced in January 2017 that were drilled closer to the western boundary of the Kakula Inferred Resource. The Kamoa-Kakula Project has started a PEA for larger production cases at both Kamoa and Kakula. The Kakula study will be based on an updated Mineral Resource Estimate expected in May 2017. It is anticipated that the increased resource base will support a Kakula mine capacity of approximately six Mtpa. The Kansoko mine capacity also is expected to be increased to six Mtpa through a change in mining method. The revised PEA targets peak mine production of approximately 12 Mtpa from the current resource base at the presently delineated Kamoa and Kakula deposits. In light of the successful step-out drilling at Kakula West, the Kamoa-Kakula development plans will be reassessed and amended on a continuous basis as the project moves forward. The updated PEA is expected to be completed in Q3 2017. Health and safety remain key priorities for all people working at the Kamoa-Kakula Project. As of March 31, 2017, the Kamoa-Kakula Project had achieved 6,394,834 lost-time injury-free man hours. During Q1 2017, 58 cases of malaria were diagnosed at the Kamoa clinic, compared to 85 for the same period in 2016. This progress is, in part, due to the project's malaria control plan. A major update to the Kamoa Environmental, Social & Health Impact Assessment (ESHIA) was submitted to DEPM (DRC environmental authority) on January 30, 2017, before the required five-year anniversary of the approved 2012 ESHIA. The scope of the updated ESHIA included the Kansoko Mine and concentrator, Kakula Mine and concentrator, Kakula tailings storage facility and main Kolwezi access road. Approval for the updated ESHIA was received from the DEPM on March 3, 2017. Ongoing exploration activities to focus on other high-priority targets As of the end of Q1 2017, more than 25,000 metres had been drilled at Kakula since the start of the year. There are 14 rigs on site, 12 of which are currently drilling; 10 from the contractor and two project-owned rigs. Included in the drilling total were holes drilled for geotechnical and metallurgical studies. Exploration activities significantly increased in Q1 2017. The accelerated exploration program was driven by resource expansion drilling to support an updated Mineral Resource Estimate planned for early Q2 2017 to be used for future development studies on the project. Nine of the 14 rigs on site were dedicated to resource expansion at Kakula. Coinciding with this expansion drilling, exploration activities were increased on untested parts of the Kamoa-Kakula licence. The Kakula West discovery was a result of the expanded grass roots program with three rigs currently dedicated to this area. With the onset of the dry season, the intention is to reallocate a number of rigs from Kakula resource expansion and development activities to test other areas on the Kamoa-Kakula licence where significant Kakula-style targets have been identified but have been inaccessible during the wet season. Figure 9: Kamoa-Kakula mining licence, showing copper grade of Indicated and Inferred Resources at a 2% copper cut-off, untested areas, current target areas and location of Kakula West Discovery: http://media3.marketwire.com/docs/1094410-F9.pdf Improved copper recoveries and concentrate grades confirmed by preliminary metallurgical tests on drill core from Kakula Following on from the positive preliminary testwork results received during Q4 2016 of 87.8% recovery at an extremely high concentrate grade of 56% copper, the next phase of flowsheet development has been initiated. A metallurgical drilling campaign to compile a representative composite sample is underway and is planned to be completed during Q3 2017. This sample will be used for the PFS circuit development and optimization testwork which is planned for the second half of 2017. Earlier metallurgical testwork indicated that the Kamoa and Kakula concentrates contain extremely low arsenic levels by world standards - approximately 0.02%. Given this critical competitive marketing advantage, Kamoa-Kakula concentrates are expected to attract a significant premium from copper-concentrate traders for use in blending with concentrates from other mines. The concentrates will help to enable the other concentrates to meet the limit of 0.5% arsenic imposed by Chinese smelters to meet China's environmental restrictions. Mine development at the Kansoko Mine expected to reach high-grade copper in Q2 Byrnecut Underground Congo SARL progressed well with the decline development at Kansoko Sud during Q1 2017. A total of more than 1,600 metres of development had been achieved at the end of Q1 2017. The service and conveyor declines each have been advanced more than 770 metres and are in Kamoa pyritic siltstone, which overlies the copper ore. Development of the underground mine is scheduled to reach the high-grade copper mineralization at the Kansoko Sud Deposit during Q2 2017. The Kamoa-Kakula technical team has identified a location for a box cut for the initial portal to planned decline ramps that will provide underground access to the Kakula Deposit. The design of the box cut has been completed and the excavation, support and civil works have been tendered. A preferred bidder has been identified and the project team is in a position to award the contract. Construction of the Kakula box cut is expected to take approximately five months, after which development of the set of twin declines can commence. A tender document for the Kakula decline development has been completed and will be issued to prospective contractors during Q2 2017. The construction of the 120 kilovolt (kV) power line that branches off from the main supply at Kisenge has been completed. A 120kV mobile substation was installed, commissioned and energized on October 30, 2016. The Kamoa mine site now is connected to the national electrical grid and is receiving hydropower for work on site. An eight-kilometre, 11kV overhead power line with mini substations has been constructed from the mine site to the Kamoa camp and is supplying hydropower to the camp. The supply of electricity from the grid has resulted in significant savings from reduced use of diesel fuel. The design of a 120kV line connecting the Kansoko mine site with Kakula has been designed and tenders from potential contractors have been received. The Mwadingusha Unit 1 repair work was completed in August 2016 and the official inauguration ceremony was held at the Mwadingusha power station on September 7, 2016. The Mwadingusha G1 unit, supplying 11 megawatts, was synchronized to the SNEL, the DRC's state-owned power company, national interconnected grid on September 6, 2016. The contract to purchase four turbines for the Mwadingusha power plant upgrades was awarded and the contract signed between SNEL and the consortium Andritz Hydro & Cegelec Corporation. A site visit by the consortium took place in December in preparation for demolition work to start in August 2017. The Sustainable Livelihoods project is largely aimed at economically empowering communities in the vicinity of the planned mine. The project, which has been in place for the past five years, continues to successfully manage the following programs during Q1 2017: The following table summarizes selected financial information for the prior eight quarters. Ivanhoe had no operating revenue in any financial reporting period and did not declare or pay any dividend or distribution in any financial reporting period. Review of the three months ended March 31, 2017 vs. March 31, 2016 The company's total comprehensive loss for Q1 2017 of $5.0 million was $2.1 million lower than for the same period in 2016 ($7.1 million). The decrease mainly was due to a $5.3 million increase in exchange gains on translation of foreign operations that was partly offset by a $2.0 million decrease in finance income. The decrease in finance income was due to the decrease in the deemed finance income on the purchase price receivable from the partial sale of the Kamoa Project from $4.3 million in Q1 2016 to $1.1 million for the same period in 2017, which coincides with the decrease in the purchase price receivable. Exploration and project expenditures for the three months ending March 31, 2017, amounted to $8.3 million and were $1.4 million more than for the same period in 2016 ($6.9 million). With the focus at the Platreef Project on development and the Kamoa Project being accounted for as a joint venture, $8.2 million of the total $8.3 million exploration and project expenditure related to the Kipushi Project. Expenditure at the Kipushi Project increased by $1.5 million compared to the same period in 2016. The company's share of losses from the Kamoa Holding joint venture increased from $4.2 million in Q1 2016 to $5.5 million in Q1 2017. The following table summarizes the company's share of the comprehensive loss of Kamoa Holding for the three months ending March 31, 2017 and for the same period in 2016: The costs associated with mine development are capitalized as development costs in Kamoa Holding, while the exploration expenditure at Kakula is expensed. The interest expense in the Kamoa Holding joint venture relates to shareholder loans where each shareholder is required to fund Kamoa Holding in an amount equivalent to its proportionate shareholding interest. Financial position as at March 31, 2017 vs. December 31, 2016 The company's total assets decreased by $3.1 million, from 1,002.2 million as at December 31, 2016, to $999.1 million as at March 31, 2017. This resulted from the company utilizing its cash resources in its operations. The company's total liabilities decreased by $2.7 million to $43.3 million as at December 31, 2017, from $46.0 million as at December 31, 2016. The remaining purchase price receivable due to the company as a result of the sale of 49.5% of Kamoa Holding decreased as the company received $41.2 million from Zijin on February 8, 2017. The present value of the remaining consideration receivable, net of transaction costs, was $38.4 million as at March 31, 2017 and is due on May 23, 2017. The company's investment in the Kamoa Holding joint venture increased by $12.5 million from $473.6 as at December 31, 2016, to $486.2 million as at December 31, 2017, with the current shareholders funding the operations equivalent to their proportionate shareholding interest. The company's portion of the Kamoa Holding joint venture cash calls amounted to $13.5 million during Q1 2017, while the company's share of comprehensive loss from joint venture amounted to $5.5 million. At Kamoa-Kakula, the focus remained on development, together with an exploration program at the Kakula Discovery. Property, plant and equipment increased by $13.5 million, with a total of $9.7 million being spent on project development and to acquire other property, plant and equipment, $9.0 million of which pertained to development costs of the Platreef Project. The company utilized $12.2 million of its cash resources in its operations and earned interest income of $0.8 million in Q1 2017. The company had $291.2 million in cash and cash equivalents as at March 31, 2017. Certain of the company's cash and cash equivalents, having an aggregate value of $10.7 million, are subject to contractual restrictions as to their use and are reserved for the Platreef Project. As at March 31, 2017, the company had consolidated working capital of approximately $338.0 million, compared to $364.8 million at December 31, 2016. The Platreef Project working capital is restricted and amounted to $5.6 million at March 31, 2017, and $14.8 million at December 31, 2016. Excluding the Platreef Project working capital, the resultant working capital was $332.4 million at March 31, 2017, and $350.0 million at December 31, 2016. The company believes it has sufficient resources to cover its short-term cash requirements. However, the company's access to financing always is uncertain and there can be no assurance that additional funding will be available to the company in the near future. On December 8, 2015, Zijin, through a subsidiary company, acquired a 49.5% interest in Kamoa Holding for a total of $412 million in a series of payments. Ivanhoe received an initial $206 million from Zijin on December 8, 2015, and a further $41.2 million on each of March 23, 2016, July 8, 2016, October 25, 2016, and February 8, 2017; the last remaining $41.2 million is scheduled to be received on May 23, 2017. Since December 8, 2015, each shareholder in Kamoa Holding has been required to fund Kamoa Holding in an amount equivalent to its proportionate shareholding interest. The company's main objectives for 2017 at the Platreef Project are the completion of the phase one feasibility study, the continuation of Shaft 1 construction and commencement of construction of Shaft 2. At Kipushi, the principal objective is the completion of the PFS and continued upgrading of mining infrastructure. At the Kamoa-Kakula Project, priorities are the continuation of drilling, the continuation of construction of the twin declines at Kamoa and the commencement of a box-cut at Kakula. The company expects to spend $50 million on further development at the Platreef Project; $26 million at the Kipushi Project; $4 million on regional exploration in the DRC; and $11 million on corporate overheads for the remainder of 2017 - as well as its proportionate funding of the Kamoa-Kakula Project, expected to be $35 million for the remainder of 2017. This news release should be read in conjunction with Ivanhoe Mines' Q1 2017 Financial Statements and Management's Discussion and Analysis report available at www.ivanhoemines.com and at www.sedar.com. Disclosures of a scientific or technical nature in this news release have been reviewed and approved by Stephen Torr, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not considered independent under NI 43-101 as he is the Vice President, Project Geology and Evaluation. Mr. Torr has verified the technical data disclosed in this news release. Ivanhoe has prepared a current independent NI 43-101-compliant technical report for each of the Platreef Project, the Kipushi Project and the Kamoa-Kakula Project, which are available under the company's SEDAR profile at www.sedar.com: These technical reports include relevant information regarding the effective dates and the assumptions, parameters and methods of the mineral resource estimates on the Platreef Project, the Kipushi Project and the Kamoa-Kakula Project cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release in respect of the Platreef Project, Kipushi Project and Kamoa-Kakula Project. Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this release. Such statements include without limitation, the timing and results of: (i) statements regarding Shaft 1 providing initial access for early underground development at the Flatreef Deposit; (ii) statements regarding the station development of Shaft 1 at the 450-, 750-, 850- and 950-metre levels; (iii) statements regarding the sinking of Shaft 1, including that a sinking rate of 45 metres per month is expected; (iv) statements regarding Shaft 1 reaching the planned, final depth at 980 metres below surface in 2018; (v) statements regarding the timing of the commencement of Shaft 2 development, including that construction of the early works is to commence in Q2 2017 and will take approximately 12 months to complete; (vi) statements regarding the operational and technical capacity of Shaft 1; (vii) statements regarding the internal diameter and hoisting capacity of Shaft 2; (viii) statements regarding the company's plans to develop the Platreef Mine in three phases: an initial annual rate of four million tonnes per annum (Mtpa) to establish an operating platform to support future expansions; followed by a doubling of production to eight Mtpa; and then a third expansion phase to a steady-state 12 Mtpa; (ix) statements regarding the planned underground mining methods of the Platreef Project including long-hole stoping and drift-and-fill mining; (x) statements regarding peak water use of 10 million litres per day at the Platreef Project and development of the Pruissen Pipeline Project; (xi) statements regarding the Platreef Project's estimated electricity requirement of 100 million volt-amperes; (xii) statements regarding the completion of a feasibility study at the Platreef Project in Q2 2017; (xiii) statements regarding the declines having been designed to intersect the high-grade copper mineralization in the Kansoko Sud area during the second quarter of 2017; (xiv) statements regarding the completion of an updated Mineral Resource Estimate at the Kamoa-Kakula Project in May 2017 and an updated preliminary economic assessment in Q3 2017; (xv) statements regarding the timing, size and objectives of drilling and other exploration programs for 2017 and future periods including a metallurgical drilling campaign at the Kakula deposit planned for Q2 2017; (xvi) statements regarding the implementation of the Social and Labour Plan at the Platreef Project and pledged expenditure of R160 million; (xvii) statements that the Kakula box-cut is expected to take approximately five months; and (xviii) statements regarding expected expenditure for the remainder of 2017 of $50 million on further development at the Platreef Project; $26 million at the Kipushi Project; $4 million on regional exploration in the DRC; and $11 million on corporate overheads - as well as its proportionate funding of the Kamoa-Kakula Project, expected to be $35 million for the remainder of 2017. As well, all of the results of the pre-feasibility study of the Kamoa-Kakula Project and preliminary economic assessment of development options for the Kakula deposit, the pre-feasibility study of the Platreef Project and the preliminary economic assessment of the Kipushi Project, constitute forward-looking statements or information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula, Platreef and Kipushi Projects, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper, nickel, zinc, platinum, palladium, rhodium and gold; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements, (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; and (xiv) political factors. This release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral Resources is inherently uncertain and involves subjective judgments about many relevant factors. Estimates of Mineral Reserves provide more certainty but still involve similar subjective judgements. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the company's projects, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that ultimately may prove to be inaccurate. Mineral Resource or Mineral Reserve estimates may have to be re-estimated based on: (i) fluctuations in copper, nickel, zinc, platinum group elements (PGE), gold or other mineral prices; (ii) results of drilling; (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the date of any estimates and/or changes in mine plans; (vi) the possible failure to receive required permits, approvals and licences; and (vii) changes in law or regulation. Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and under "Risk Factors", as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations. Although the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release. The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth in the "Risk Factors" section of the company's Q1 2017 MD&A.


The Initial Kakula Mineral Resource Estimate Vaults the Kamoa-Kakula Project Into the Ranks of the World's 10 Largest Copper Deposits; Its Copper Grades Are the Highest of the Top 10, by a Wide Margin TORONTO, CANADA--(Marketwired - Nov. 10, 2016) - Ivanhoe Mines (TSX:IVN)(OTCQX:IVPAF) today announced its financial results for the third quarter ended September 30, 2016. All figures are in US dollars unless otherwise stated. The Platreef Project is owned by Ivanplats (Pty) Ltd, which is 64%-owned by Ivanhoe Mines. A 26% interest is held by Ivanplats' historically-disadvantaged broad-based, black economic empowerment (B-BBEE) partners, which include 20 local host communities with a total of approximately 150,000 people, project employees and local entrepreneurs. Ivanplats reconfirmed its Level 3 status in its second verification assessment on a B-BBEE scorecard. A Japanese consortium of ITOCHU Corporation and its affiliate, ITC Platinum, plus Japan Oil, Gas and Metals National Corporation and JGC Corporation, owns a 10% interest in Ivanplats, which it acquired in two tranches for a total investment of $290 million. The Platreef Project hosts an underground deposit of thick, platinum-group metals, nickel, copper and gold mineralization in the Northern Limb of the Bushveld Igneous Complex, approximately 280 kilometres northeast of Johannesburg and eight kilometres from the town of Mokopane in Limpopo Province. Since 2007, Ivanhoe has focused its exploration activities on defining and advancing the down-dip extension of its original discovery at Platreef, now known as the Flatreef Deposit, which is amenable to highly mechanized, underground mining methods. The Flatreef area lies entirely on the Turfspruit and Macalacaskop properties, which form part of the company's mining right. The Platreef Project reached a total of 6,331,141 million hours in terms of the Mines Health and Safety Act and the Occupational Health and Safety Act (OHSA) by the end of September 2016. The project recorded 178,552 work hours free of lost-time injuries (LTIF) up until the end of Q3 2016. Unfortunately, the project suffered a lost-time injury during the quarter. A rock-drill operator was injured, booked off and returned to work seven days after the incident. The Platreef Project continues to strive toward its workplace objective of an environment that causes zero harm to any employees, contractors, sub-contractors or consultants. Shaft 1, with an internal diameter of 7.25 metres, will provide initial access to the ore body and enable the initial underground capital development to take place during the development of Shaft 2, the main production shaft. Following the successful commissioning and licencing of the stage and kibble winders and ancillary equipment, the permanent sinking phase started in July 2016. The initial sinking phase was completed to 107 metres below surface and the main sinking phase has been initiated. A sinking rate of 45 metres per month is expected during the main phase, which includes a 300-millimetre concrete shaft lining and inserts. The current level is approximately 130 metres below surface; stations will be developed at the 450-, 750-, 850- and 950-metre levels. The main sinking phase is expected to reach its projected, final depth of 980 metres below surface in 2018. To view Figure 1. Shaft 1 headgear and other related surface infrastructure, please visit the following link: http://media3.marketwire.com/docs/1076002fig1.jpg Work is complete on the internal substation, which has a capacity of five million volt-amperes (MVA). Construction is underway on the power transmission lines from Eskom, South Africa's public electricity utility, which are expected to supply the electricity for shaft sinking. Back-up generators have been installed to ensure continued sinking operations during any interruptions in Eskom's supply of electricity. The new transmission lines also are expected to provide power to an adjacent community near the Platreef Project, which will be a major, added community benefit. To view Figure 2. Eskom's 5MVA line to Platreef Project, please visit the following link: http://media3.marketwire.com/docs/1076002f2.jpg Other on-site work completed includes the storm-water pond management system, concrete batch plant, workshops, stores and an explosives magazine. Construction of the intersection on the National Road (N11) highway for improved access to the Platreef mine site was completed in August 2016. The work included adding extra lanes to the existing roadway, exit and entry ramps, storm-water management and resurfacing of the intersection. Ivanhoe plans to develop the Platreef Mine in phases. The initial annual rate of four million tonnes per annum (Mtpa) is designed to establish an operating platform to support future expansions. This is expected to be followed by a potential doubling of production to 8 Mtpa; and then a third expansion phase to a steady-state 12 Mtpa, which would establish Platreef among the largest platinum-group-metals mines in the world. Ivanhoe has made good progress on advancing the feasibility study of the first phase, which began in August 2015. The study is being managed by DRA Global - with specialized sub-consultants including Stantec Consulting, Murray & Roberts Cementation, SRK, Golder Associates and Digby Wells Environmental - and is expected to be completed in the first half of 2017. There are expected to be opportunities to refine and modify the timing and capacities of subsequent phases of production to suit market conditions during the development and commissioning of the first phase. The selected mining areas in the current mine plan occur at depths ranging from approximately 700 metres to 1,200 metres below the surface. The main access to the Flatreef Deposit and ventilation system is expected to be through four vertical shafts. Shaft 2 will host the main personnel transport cage, material and ore-handling systems; Shafts 1, 3 and 4 will provide ventilation to the underground workings. Shaft 1, now under development, also will be used for initial access to the deposit and early underground development. Planned mining of the Flatreef Deposit is expected to use highly productive, mechanized methods, including long-hole stoping and drift-and-fill mining. Mined-out areas will be backfilled with a paste mixture that utilizes tailings from the process plant and cement. The ore will be hauled from the stopes to a series of ore passes that will connect to a main haulage level at Shaft 2, from where it will be hoisted to surface for processing. The Olifants River Water Resource Development Project (ORWRDP) is designed to deliver water to the Eastern and Northern limbs of South Africa's Bushveld Complex. The project consists of the new De Hoop Dam, the raised wall of the Flag Boshielo Dam and related pipeline infrastructure that ultimately is expected to deliver water to Pruissen, southeast of the Northern Limb. The Pruissen Pipeline Project is expected to be developed to deliver water onward from Pruissen to the municipalities, communities and mining projects on the Northern Limb. Ivanhoe is a member of the ORWRDP's Joint Water Forum. The Minister of Water & Sanitation has directed that the Trans-Caledon Tunnel Authority serve as the implementing agent for the outstanding phases of the ORWRDP scheme, which include the Phase 2B pipeline from Flag Boshielo Dam to Mokopane. The Platreef Project's water requirement for the first phase of development is projected to peak at approximately 10 million litres per day, which is expected to be serviced by the scheme. Ivanhoe also is investigating various alternative sources of bulk water, including an allocation of bulk grey-water from the local municipality. The Platreef Project's electricity requirement for a four-million-tonne-per-year underground mine, concentrator and associated infrastructure has been estimated at approximately 100 million volt-amperes. An agreement has been reached with Eskom for the supply of phase-one power. Ivanhoe chose a self-build option for permanent power that will enable the company to manage the construction of the distribution lines from Eskom's Burutho sub-station to the Platreef Mine. The formulation of the self-build and electrical supply agreements are in progress. Work is progressing well on the further implementation of Ivanhoe's Social and Labour Plan (SLP), to which the company has pledged a total of R160 million ($11 million) during the first five years, until November 2019. The approved plan includes R67 million ($4 million) for the development of job skills among local residents and R88 million ($6 million) for local economic development projects. Additional internal training is ongoing to provide members of the current workforce with opportunities to expand their skills. Ivanplats recently concluded a one-year deal with the National Union of Mineworkers (NUM) for annual wage increases without any labour disruption or work stoppage during negotiations. The Kipushi copper-zinc-germanium-lead mine, in the Democratic Republic of Congo, is adjacent to the town of Kipushi and approximately 30 kilometres southwest of Lubumbashi. It is located on the Central African Copperbelt, approximately 250 kilometres southeast of the Kamoa-Kakula Project and less than one kilometre from the Zambian border. Ivanhoe acquired its 68% interest in the Kipushi Project in November 2011; the balance of 32% is held by the state-owned mining company, La Générale des Carrières et des Mines (Gécamines). The Kipushi Project achieved a total of 4,674,445 work hours free of lost-time injuries, equivalent to 1,512 days, to the end of Q3 2016. Malaria remains the most frequently occurring health concern at Kipushi; in Q3 2016, there was an average of 15 cases each month among employees, which is above the dry-season norm. In an effort to reduce the incidence of malaria in the Kipushi community, a Water Sanitation and Health (WASH) program has been initiated in cooperation with the Territorial Administrator and the local community. The main emphasis of the program's first phase is cleaning storm drains in the municipality to prevent the accumulation of ponded water, where malarial mosquitos breed. The Fionet program to combat malaria has distributed 150 Deki electronic readers in addition to the original 37 readers provided to medical-service providers in Lualaba and Haut-Katanga provinces. The Deki technology provides automated reading of Rapid Diagnostic Tests to remove the human-error factor and prescription of unnecessary medication and uploads data to a cloud server for analysis by the Ministry of Health in planning malaria-control measures. Data gathered up until September 30, 2016, indicate that 18,818 patients have been tested using the Deki reader, with more than half those testing negative for malaria. The Kipushi Mine, which had been placed on care and maintenance in 1993, flooded in early 2011 due to a lack of pump maintenance over an extended period. At its peak, water reached 851 metres below the surface. A major milestone was reached in December 2013 when Ivanhoe restored access to the mine's principal haulage level at 1,150 metres below the surface. Since then, crews have been upgrading underground infrastructure to permanently stabilize the water levels. Since completion of the drilling program, water levels have been lowered to approximately the 1,245-metre-level in Shaft 5. Engineering work has focused on upgrading of Shaft 5 conveyances and infrastructure, cleaning the shaft bottom to facilitate the installation of new hoist ropes, repairs and upgrades to the hoisting infrastructure and cleaning and stripping of the main pump station at the 1,200-metre-level. To view Figure 3. Connecting discharge pipes to one of five pumps on the 1,200-metre-level, please visit the following link: http://media3.marketwire.com/docs/1076002f3.jpg A pre-feasibility study (PFS) now underway will further refine the optimal development scenario for the existing underground mine at Kipushi. Orewin Pty. Ltd., of Australia, has been appointed the main contractor and Golder Associates, MDM, SRK, DRA and Grindrod have been engaged to complete various aspects of the PFS. The PFS will refine the positive preliminary economic assessment (PEA) for the redevelopment of the Kipushi Project that was announced on May 2, 2016. The PEA was prepared in compliance with Canadian National Instrument 43-101 - Standards of Disclosure for Mineral Projects. Highlights of the PEA, prepared by OreWin and the MSA Group (Pty) Ltd, of Johannesburg, South Africa, include: The Kamoa-Kakula Copper Project, a joint venture between Ivanhoe Mines and Zijin Mining, is the largest copper discovery ever made on the African continent, with adjacent prospective exploration areas within the Central African Copperbelt in the Democratic Republic of Congo, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of Lubumbashi. Ivanhoe sold a 49.5% share interest in Kamoa Holding Limited, the company that presently owns 95% of Kamoa Copper SA, the owner of the Kamoa-Kakula Project, to Zijin Mining in December 2015 for an aggregate consideration of $412 million. In addition, Ivanhoe sold a 1% share interest in Kamoa Holding to privately-owned Crystal River Global Limited for $8.32 million - which Crystal River will pay through a non-interest-bearing, 10-year promissory note. A 5%, non-dilutable interest in the Kamoa-Kakula Project was transferred to the DRC government on September 11, 2012, for no consideration, pursuant to the DRC Mining Code. Ivanhoe also has offered to transfer an additional 15% interest to the DRC government on terms to be negotiated. Constructive and cordial negotiations over the offer are continuing between Ivanhoe Mines, Zijin and senior DRC government officials. Ivanhoe expects a mutually beneficial agreement to be achieved in the near future that will provide long-lasting, positive benefits to the DRC government and the Congolese people. Subsequent to the sales to Zijin and Crystal River, Ivanhoe owns an effective 47% of the Kamoa-Kakula Project, which will decrease to an effective 40% should the additional 15% interest be transferred to the DRC government. Kamoa-Kakula already ranks among the 10 largest copper deposits in the world. On October 12, 2016, an initial Mineral Resource estimate for the extremely-high-grade Kakula Discovery was issued with an effective date of October 9, 2016. The combined Kamoa-Kakula Indicated Mineral Resources now total 944 million tonnes grading 2.83% copper, containing 58.9 billion pounds of copper at a 1.0% copper cut-off grade and a minimum thickness of three metres. Kamoa-Kakula now also has Inferred Mineral Resources of 286 million tonnes grading 2.31% copper and containing 14.6 billion pounds of copper, also at a 1.0% copper cut-off grade and a minimum thickness of three metres. The mining portion of the feasibility study for a four-million-tonne-per-annum (4 Mtpa) mine at Kansoko Sud is progressing well; the work is being carried out by a number of specialist consultants, including Stantec for the mine, DRA for the underground engineering, KGHM Cuprum for geotechnical and mining method, SRK for the mine geotechnical and Golder for geohydrology. With the initial Kakula Mineral Resource estimate completed, Kamoa Copper has retained OreWin, of Adelaide, Australia, to prepare a preliminary economic assessment (PEA) for the development of the Kakula Deposit. The PEA, which is expected to be completed before the end of 2016, will concentrate on establishing the economic parameters of potential mining operations at Kakula, including capital and operating costs for an underground mine. The PEA will draw on recommendations from the Kamoa 2016 pre-feasibility study, including the potential to increase production to up to four million tonnes per year from the proposed initial mining area. Recent bench-scale metallurgical flotation test work carried out at XPS Consulting and Testwork Services laboratories in Falconbridge, Canada, achieved copper recoveries of 87.8% and produced a concentrate with an extremely high grade of 56% copper using the flowsheet developed during the Kamoa pre-feasibility study. The material tested was a composite of recent, chalcocite-rich Kakula drill core, assaying 8.1% copper. Kakula mineralization is characteristically bottom loaded. The Resource estimate demonstrates that opportunities exist to mine Kakula at much higher lateral and vertical cut-offs than at Kamoa's Kansoko Sud. The clear zonation and grades in the central high-grade core should provide sequencing opportunities to mine at significantly elevated grades. Health and safety remain key priorities for all people working at the Kamoa-Kakula Project, where an excellent safety record has been achieved. As of September 30, 2016, a total of 5,590,040 hours had been worked without a lost-time injury. Exploration activities lead to a substantial expansion of the Kakula Discovery On October 12, 2016 the company released the initial Resource estimate for its Kakula Discovery at the Kamoa-Kakula Project. Highlights of the initial Kakula Mineral Resource estimate, prepared by Ivanhoe Mines under the direction of Amec Foster Wheeler E&C Services Inc., of Reno, USA, in accordance with the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves are: The Kakula Mineral Resource has been defined by drilling covering a total area of 8.7 square kilometres within the larger 60-square-kilometre Kakula Exploration Area, as shown in Figure 4. The total areal extent of Indicated Resource is 4.6 square kilometres at a 1% cut-off and the areal extent of the Inferred Resource is 3.3 square kilometres at a 1% cut-off. The average dip of the mineralized zone in the Indicated Resource area is 13 degrees, while the average dip is 16 degrees in the Inferred Resource area. The high-grade copper mineralization remains open for significant expansion along trend to the northwest. The remainder of the Kakula Exploration Area remains untested (see Figure 4). The Mineral Resource estimate is based on the results from approximately 24,000 metres of drilling in 65 holes. An additional 13 holes totalling more than 7,000 metres have been completed and assay results are pending. Indicated Resources are defined when the drill-hole spacing approximates a 400-metre grid, while Inferred Resources are defined when the drill-hole spacing approximates an 800-metre grid. To view Figure 4. Kamoa-Kakula Project map showing location of Kakula exploration and initial Kakula Resource outline, please visit the following link: http://media3.marketwire.com/docs/1076002f4.jpg Kakula's estimated Resources are in addition to the Mineral Resources delineated elsewhere on the Kamoa mining licence that were disclosed by Ivanhoe Mines in a news release on February 23, 2016. The combined Kamoa-Kakula Indicated Mineral Resources now total 944 million tonnes grading 2.83% copper, containing 58.9 billion pounds of copper at a 1.0% copper cut-off grade and a minimum true thickness of three metres. Kamoa-Kakula now also has Inferred Mineral Resources of 286 million tonnes grading 2.31% copper and containing 14.6 billion pounds of copper, also at a 1.0% copper cut-off grade and a minimum true thickness of three metres. Exploration activities lead to significant expansion of the Kakula Discovery and a substantial increase in the planned scope of exploration activities for 2016 and 2017 During Q3 2016, a total of 19,418 metres of exploration drilling was completed at the new Kakula Discovery. A total of 17,702 metres was completed by the drilling contractor, Titan Drilling SARL, utilizing up to six drill rigs; an additional 1,716 metres was completed using company-owned drill rigs. Included in the drilling program were holes drilled for geotechnical studies as well as PQ drill holes for comminution test work. In addition to the exploration program, 185 metres were completed for dewatering of the Kansoko Sud declines. A total of 220 metres was completed by Titan Drilling for cover drilling within the declines ahead of the mine development. This program is planned to continue for the duration of the decline development. Drilling for 2016 now totals 33,443 metres. As a result of the ongoing success of the Kakula drilling program and the extension along trend of the central, high-grade, chalcocite-rich core to the northwest and southeast at relatively shallow depths, the Kakula drilling program was expanded in Q2 by an additional 9,000 metres, to a total of 34,000 metres. With the completion of the initial Mineral Resource estimate and the significance of the discovery now firmly established, the Kakula exploration program has been significantly expanded by a further 60,000 metres. The expanded program is planned to run through to the end of Q2 2017 and will consist of infill drilling, resource expansion and exploration of the Kakula Discovery area. The expanded drill program will be completed by a combination of contractor drilling and company-owned rigs. Byrnecut Underground Congo SARL progressed well with the decline development at Kansoko during Q3 2016 and is advancing ahead of schedule. The twin declines, incorporating both a service and a conveyor tunnel, each have advanced more than 365 metres. To view Figure 5. Kansoko box-cut sump being cleaned and equipped, please visit the following link: http://media3.marketwire.com/docs/1076002f5.jpg Development of the underground mine is designed to reach the high-grade copper mineralization at the Kansoko Sud deposit during the first quarter of 2017. The development is ahead of schedule and within budgeted costs. During the quarter, the settling and clean-water dams were constructed and equipped, and the first cross-cut between the declines was blasted. The box-cut sump also was cleaned and equipped with permanent pumps and a pump column. To view Figure 6. Underground loading operation, please visit the following link: http://media3.marketwire.com/docs/1076002f6.jpg In parallel with the Kamoa 2016 PFS, an alternative mining method - controlled-convergence room-and-pillar mining, developed by Poland-based KGHM - was investigated for potential use on the Kansoko deposits. Given the thick, mineralized widths encountered to date in the Kakula drilling program, controlled-convergence room-and-pillar mining also will be investigated for potential use at Kakula. To help advance the ongoing exploration and development of the Kakula Deposit, the Kamoa engineering team has identified a possible location for a box cut at Kakula. The design of the box cut is underway and the preparation of tender documents for the excavation, support and civil works is underway. A 10-kilometre road from the Kamoa mine site to Kakula is under construction to facilitate access for drill rigs and construction equipment during the rainy season. To view Figure 7. The new Kakula access road under construction, please visit the following link: http://media3.marketwire.com/docs/1076002f6.jpg The Mwadingusha Unit 1 repair work was completed in August 2016 and the official inauguration ceremony took place on September 7, 2016, at the Mwadingusha power station. The Mwadingusha G1 unit, supplying 11MW, was synchronized to the national interconnected grid on September 6, 2016. The following table summarizes selected financial information for the prior eight quarters. Ivanhoe had no operating revenue in any financial reporting period and did not declare or pay any dividend or distribution in any financial reporting period. Review of the three months ended September 30, 2016 vs. September 30, 2015 The company's total comprehensive loss for Q3 2016 of $0.6 million was $12.3 million lower than for the same period in 2015 ($12.9 million). The decrease mainly was due to exchange gains on translation of foreign operations recognized in Q3 2016 of $10.8 million resulting from the strengthening of the South African Rand by 10% from June 30, 2016, to September 30, 2016. Finance income increased by $7.0 million in Q3 2016 when compared to the same period in 2015 and mainly included interest earned on loans to the Kamoa joint venture that amounted to $4.2 million and deemed income on the purchase price receivable from the partial sale of the Kamoa-Kakula Project that amounted to $2.3 million. Exploration and project expenditures for the three months ending September 30, 2016, amounted to $7.8 million and were $0.8 million less than for the same period in 2015 ($8.6 million). With the focus at the Platreef Project on development, and the Kamoa-Kakula Project being accounted for as a joint venture, $7.5 million of the total $7.8 million exploration and project expenditure related to the Kipushi Project. Expenditure at the Kipushi Project decreased by $0.4 million compared to the same period in 2015. Review of the nine months ended September 30, 2016 vs. September 30, 2015 The company's total comprehensive loss of $17.7 million for the nine months ended September 30, 2016, was $28.7 million lower than for the same period in 2015 ($46.4 million). The decrease was due to exchange gains on translation of foreign operations of $10.4 million recognized in the first nine months of 2016 compared to an exchange loss on translation of foreign operations of $11.7 million for the same period in 2015. The increase in finance income of $22.1 million, together with a $7.6 million decrease in exploration and project expenditure, also contributed to the decreased comprehensive loss for the period, but was partly offset by the company's share of losses from its Kamoa joint venture that amounted to $15.8 million. Finance income for the nine months ending September 30, 2016, amounted to $23.1 million, which was $22.1 million more than for the same period in 2015 ($1.0 million). The increase mainly was due to interest earned on loans to the Kamoa joint venture that amounted to $11.5 million for the nine months ending September 30, 2016, together with deemed finance income on the purchase price receivable from the partial sale of the Kamoa-Kakula Project, which amounted to $9.5 million. Exploration and project expenditures for the nine months ending September 30, 2016, amounted to $22.9 million and were $7.6 million less than for the same period in 2015 ($30.5 million). The $4.1 million retrenchment costs incurred in 2015 relating to the closure of Ivanhoe's regional exploration company in the DRC was the main reason for the decrease, together with reduced expenditure at the Kipushi Project. With the focus at the Platreef Project on development and the Kamoa-Kakula Project being accounted for as a joint venture, $22.2 million of the total $22.9 million exploration and project expenditure related to the Kipushi Project. Expenditure at the Kipushi Project decreased by $2.8 million compared to the same period in 2015. Financial position as at September 30, 2016 vs. December 31, 2015 The company's total assets decreased by $16.4 million, from $1,022.6 million as at December 31, 2015, to $1,006.2 million as at September 30, 2016. This resulted from the company utilizing its cash resources in its operations. The remaining purchase price receivable due to the company as a result of the sale of 49.5% of Kamoa Holding decreased as the company received $93.1 million from Zijin during the nine months ending September 30, 2016. The present value of the remaining consideration receivable, net of transaction costs, was $113.4 million as at September 30, 2016. Ivanhoe received $41.2 million of the remaining consideration receivable subsequent to September 30, 2016, on October 25, 2016, and the next of the two remaining installments is due on February 8, 2017. The company's investment in the Kamoa Holding joint venture increased by $43.8 million from $412.0 as at December 31, 2015, to $455.8 million as at September 30, 2016, with the current shareholders funding the operations equivalent to their proportionate shareholding interest. At Kamoa-Kakula, the focus remained on development, together with an exploration program at the Kakula Discovery. Property, plant and equipment increased by $37.7 million, with a total of $32.4 million being spent on project development and to acquire other property, plant and equipment, $29.7 million of which pertained to development costs of the Platreef Project. The company utilized $24.8 million of its cash resources in its operations and earned interest income of $2.1 million on cash balances in the nine months ended September 30, 2016; the company's portion of the Kamoa joint venture cash calls amounted to $47.1 million. The company's total liabilities decreased to $40.9 million as at September 30, 2016, from $43.8 million as at December 31, 2015. This mainly was due to the decrease in trade and other payables of $3.9 million. The company had $275.9 million in cash and cash equivalents as at September 30, 2016. Certain of the company's cash and cash equivalents, having an aggregate value of $29.1 million, are subject to contractual restrictions as to their use and are reserved for the Platreef Project. As at September 30, 2016, the company had consolidated working capital of approximately $401.9 million, compared to $424.6 million at December 31, 2015. The Platreef Project working capital is restricted and amounted to $28.8 million at September 30, 2016, and $53.2 million at December 31, 2015. Excluding the Platreef Project working capital, the resultant working capital was $373.1 million at September 30, 2016, and $371.4 million at December 31, 2015. The company believes it has sufficient resources to cover its short-term cash requirements. However, the company's access to financing always is uncertain and there can be no assurance that additional funding will be available to the company in the near future. On December 8, 2015, Zijin completed its investment in Ivanhoe's Kamoa-Kakula Copper Project. Zijin, through a subsidiary company, has acquired a 49.5% interest in Kamoa Holding for a total of $412 million in a series of payments. Ivanhoe received an initial $206 million from Zijin on December 8, 2015 and a further $41.2 million on each of March 23, 2016, July 8, 2016, and October 25, 2016; the remaining $82.4 million is scheduled to be received in two equal installments, payable every 3.5 months from the previous installment. Upon closing of the transaction, each shareholder is required to fund Kamoa Holding in an amount equivalent to its proportionate shareholding interest. The company's main objectives for 2016 at the Platreef Project remain the continuation of the phase one feasibility study and Shaft 1 construction. At Kipushi, the principal objective is the continued upgrading of mining infrastructure, now that the preliminary economic assessment has been successfully completed. At the Kamoa-Kakula Project, priorities are the continuation of drilling and the construction of the twin declines at Kamoa. The company expects to spend $14 million on further development at the Platreef Project; $8 million at the Kipushi Project; and $5 million on corporate overheads for the remainder of 2016. The company's proportionate funding of the Kamoa-Kakula Project for Q4 2016 already has been advanced in September; however, funding for Q1 2017 is expected to be advanced in December 2016. This release should be read in conjunction with Ivanhoe Mines' unaudited, condensed, consolidated interim financial statements for the three and nine months ended September 30, 2016, and Management's Discussion and Analysis (MD&A) report available at www.ivanhoemines.com and at www.sedar.com. Disclosures of a scientific or technical nature in this news release have been reviewed and approved by Stephen Torr, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not considered independent under NI 43-101 as he is the Vice President, Project Geology and Evaluation. Mr. Torr has verified the technical data disclosed in this release. Ivanhoe has prepared a current independent, NI 43-101-compliant technical report for each of the Platreef Project, the Kipushi Project and the Kamoa-Kakula Project, which are available under the company's SEDAR profile at www.sedar.com. These technical reports include relevant information regarding the effective dates and the assumptions, parameters and methods of the mineral resource estimates on the Platreef Project, the Kipushi Project and the Kamoa-Kakula Project cited in this release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this release in respect of the Platreef Project, Kipushi Project and Kamoa-Kakula Project. Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws, including without limitation, the timing and results of: (i) statements regarding Shaft 1 providing initial access for early underground development at the Flatreef Deposit; (ii) statements regarding the station development of Shaft 1 at the 450, 750, 850 and 950 metre levels; (iii) statements regarding the sinking of Shaft 1, including that a sinking rate of 45 metres per month is expected; statements regarding Shaft 1 reaching the planned, final depth at 980 metres below surface in 2018; (iv) statements regarding the timing of the commencement of Shaft 2 development, including that construction is to commence in 2017; (v) statements regarding the operational and technical capacity of Shaft 1; (vi) statements regarding the internal diameter and hoisting capacity of Shaft 2; (vii) statements regarding the Company's plans to develop the Platreef Mine in three phases: an initial annual rate of four million tonnes per annum (Mtpa) to establish an operating platform to support future expansions; followed by a doubling of production to eight Mtpa; and then a third expansion phase to a steady-state 12 Mtpa; (viii) statements regarding the planned underground mining methods of the Platreef Project; (ix) statements regarding peak water use of 10 million litres per day at the Platreef Project and development of the Pruissen Pipeline Project; (x) statements regarding the Platreef Project's electricity requirement of 100 million volt-amperes; (xi) statements regarding the completion of a feasibility study at the Platreef Project in the first half of 2017; (xii) statements regarding the declines having been designed to intersect the high-grade copper mineralization in the Kansoko Sud area during the first quarter of 2017; (xiii) statements regarding the timing, size and objectives of drilling and other exploration programs for 2016 and future periods; (xiv) statements regarding the expectation to have a preliminary economic assessment (PEA) of the Kakula Discovery at the Kamoa-Kakula Project completed before the end of 2016; (xv) statements regarding the implementation of Social and Labour Plan at the Platreef Project; (xvi) statements that the expanded 60,000 metres of drilling at the Kakula Discovery will run through Q2 2017; and (xvii) statements regarding expected further expenditure in 2016 of $14 million on further development at the Platreef Project; $8 million at the Kipushi Project; and $5 million on corporate overheads - as well as its proportionate funding of the Kamoa-Kakula Project for Q1 2017 expected to be advanced in December 2016. Such statements involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this news release. As well, the results of the pre-feasibility study of the Kamoa-Kakula Project, the pre-feasibility study of the Platreef Project and the preliminary economic assessment of the Kipushi Project constitute forward-looking information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula, Platreef and Kipushi Projects, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper, nickel, zinc, platinum, palladium, rhodium and gold; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements, (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; and (xiv) political factors. This news release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral Resources is inherently uncertain and involves subjective judgments about many relevant factors. Estimates of Mineral Reserves provide more certainty but still involve similar subjective judgements. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the company's projects, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that ultimately may prove to be inaccurate. Mineral Resource or Mineral Reserve estimates may have to be re-estimated based on: (i) fluctuations in copper, nickel, zinc, platinum group elements (PGE), gold or other mineral prices; (ii) results of drilling; (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the date of any estimates and/or changes in mine plans; (vi) the possible failure to receive required permits, approvals and licenses; and (vii) changes in law or regulation. Forward-looking statements involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including, but not limited to, the factors discussed below and under "Risk Factors", as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations. Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release. The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth in the "Risk Factors" section and elsewhere in the company's MD&A.


Rwasoka D.T.,Upper Manyame Subcatchment Council | Madamombe C.E.,Digby Wells Environmental | Gumindoga W.,Box MP | Kabobah A.T.,University of Energy and Natural Resources
Physics and Chemistry of the Earth | Year: 2014

Hydrologic modelling lies at the core of hydrology and water resources management. Attempts at gaining a holistic grasp on model robustness, hydrologic theory and processes have inadvertently led to models that are not-well structured or too complex to apply in arid and semi-arid catchments and in Africa, in particular. In view of this, this paper reports on the application of a monthly parsimonious hydrologic model in two catchments in Zimbabwe, the Nyatsime and Upper Save river catchments. The two (2) parameter monthly parsimonious GR2M model was applied. The inputs were rainfall and potential evapotranspiration. Measured discharge was used for calibration and validation. Calibration and uncertainty analysis were done using the Differential Evolution Adaptive Metropolis (DREAM) algorithm. The performance of the GR2M model was evaluated using ten (10) model performance metrics. Parameter indentifiability was analysed on the basis of the shape of the posterior distribution of parameters. Parameter and total uncertainty were analysed in the context of the formal Bayesian DREAM approach. The 10 performance evaluation metrics showed that the model performed satisfactorily during calibration and validation in terms of the overall fit of observed and simulated stream flows, low flows and the runoff volumes. The Nash-Sutcliffe efficiency (NSE) was >0.85, the Kling-Gupta Efficiency (KGE) was >80% and Volume Efficiency was >59% during calibration. Slight performance drops were noted during validation except for the NSE in Nyatsime catchment whilst the KGE remained relatively high. The validation NSE was >0.65, the Kling-Gupta Efficiency (KGE) was >71% and Volume Efficiency was >55%. Calibrated parameters values showed good time-stability and were well identifiable with posterior parameter distributions having Gaussian shapes. Parameter uncertainty, in relation to total uncertainty was low. Parameter uncertainty constituted about 7% of the total uncertainty region. It was concluded that, although the model only had two parameters, the model performed quite satisfactorily in the simulation of monthly flows which makes it a good tool for operational hydrology and water resources modelling, planning and management especially in regions with inadequate data. © 2013 Elsevier Ltd.


Molwantwa J.B.,Digby Wells Environmental | Rose P.D.,Rhodes University
Water SA | Year: 2013

Where sulphate removal is targeted in the biological treatment of acid mine drainage wastewaters, a step additional to sulphate reduction is required to prevent the complete oxidation of sulphide back to sulphate. This linearisation of the biological sulphur cycle has presented a technological bottleneck, particularly in passive treatment operations. We report an investigation of sulphur production in floating sulphur biofilms as a means for addressing this problem. These 50 μm to 500 μm structures may be seen to form on the surface of sulphidic, organic waters and in which sulphide is partly oxidised to So and polysulphide. A Linear Flow Channel Reactor was developed in which the formation of the floating sulphur biofilm could be optimised and studied under controlled conditions. In this study the sulphide feed was sourced from a lignocellulose packed bed reactor treating a synthetic acid mine water (2 000 mg·ℓ-1 Na2SO4 solution) and the Liner Flow Channel Reactors (surface area 1.1 m2 and 2.2 m2) were operated in a controlled environment chamber. The floating sulphur biofilm was harvested by settling to the bottom of the reactor where it remained largely unreacted until removed. It was shown that up to 88% of sulphide in the feed stream may be removed in this way and that this was achieved mainly by oxidation of sulphide to sulphur (including a polysulphide fraction). A mass balance accounting for the process showed that up to 66% of total sulphur species entering the system were recovered as So. Oxidation of sulphide to thiosulphate and sulphate was not found to be significant. A fraction of fine particulate sulphur is released into the stream on harvesting of the biofilm which does not readily settle in the reactor and may thus be lost to the mass balance account. The effects of temperature, loading rate and reactor surface area were investigated in optimising the performance of the reactor. Scale-up application studies in the use of the Linear Flow Channel Reactor in an acid mine drainage passive treatment environment have been undertaken in field studies.


Tate R.B.,Digby Wells Environmental | Husted A.,Digby Wells Environmental
African Journal of Aquatic Science | Year: 2014

Given the importance of fish as a source of protein and the potential for exposure of humans to metal elements, metal bioaccumulation concentrations in Tilapia zillii from four sites in the Badeni Dam on the Badeni River, Côte d'Ivoire, were analysed in March 2013. There were no significant differences between sites and therefore mean values for the impoundment as a whole were used to compare data with those from the literature. Comparative analysis showed elevated levels of manganese, iron, zinc, copper and cadmium from fish in this study. Due to the absence of human influence in the catchment area, these elevated levels are attributed to the unique geological characteristics of the catchment, compounded by the impoundment conditions. Further studies on fish condition to ascertain the effects of the elevated metal concentrations are recommended. © 2014 Copyright © NISC (Pty) Ltd.


Tate R.B.,Digby Wells Environmental | Husted A.,Digby Wells Environmental
African Journal of Aquatic Science | Year: 2015

The upper Boesmanspruit river system received much attention in 2012 when a pollution event in January rendered the drinking water of the town of Carolina non-potable. The responses of aquatic macroinvertebrate assemblages in the upper Boesmanspruit system to that event were investigated in 2012–2013. Water quality was fair during the survey periods. Macroinvertebrate responses in the Witrandspruit, a tributary of the Boesmanspruit, showed slow recovery in the lower reaches and slight recovery in the upstream areas, demonstrating the intensity of the pollution event at the downstream sites and indicating continued toxicity. Overall, macroinvertebrate assemblage indices were modified and poor, representing recent and historical events within each river catchment. Despite a 15-month period of improved water quality after January 2012, the macroinvertebrate communities had recovered only slightly. Continued monitoring of macroinvertebrates in the study area is recommended, so as to investigate further the recovery periods of macroinvertebrates in the South African highveld. © 2015, Copyright © NISC (Pty) Ltd.

Loading Digby Wells Environmental collaborators
Loading Digby Wells Environmental collaborators